Macroplan
A Macroplan is a week-by-week plan that keeps the receipts: what we promised to deliver, when it actually landed, and what the gap taught us — a simpler cousin of a Gantt chart whose purpose is not just scheduling but learning.
Language
Macroplan: A week-by-week plan that keeps the receipts on the Features we promised: when each actually landed, and what the gap taught us. Avoid: Gantt, roadmap, timeline
Feature: A unit of delivery with a start week, an Original Estimate, optional Re-estimates, and (eventually) a Delivery. Avoid: task, ticket, story, epic
Original Estimate:
The first committed delivery week for a Feature. The immovable baseline against which on-time vs. late is judged. Rendered ◯ while unmet.
Avoid: target, deadline, due date
Re-estimate:
A revised, later delivery week recorded when a Feature will miss a prior estimate. A visible slip; it never moves the Original Estimate baseline. Rendered △.
Avoid: reschedule, new deadline
Delivery:
The week a Feature was actually completed. On-time (delivered on/before the Original Estimate) renders ◉; late renders ▲.
Avoid: completion, done date, release
Milestone: An external event or date that explicitly names a set of Features that must be delivered by it. Rendered as a labelled vertical line across the plan. Carries no rolled-up status of its own — whether it will be hit is read off its Features. Avoid: deadline, release, gate
Learning: A free-text takeaway captured against a Feature once it is delivered — what this delivery taught us to do better next time. Shown in a persistent trailing column per row; empty for in-flight Features. Avoid: retro note, lesson, postmortem
Status: A Feature's current delivery confidence (a snapshot, overwritten each review): on-track (all good), at-risk (in trouble but we have a plan), off-track (in trouble and we have no plan). May carry a comment. Applies only while in-flight; once delivered, the Learning takes over and the Status is dropped. An overdue Feature (past its latest estimate, not delivered) is expressed through an at-risk/off-track Status, not a dedicated symbol. Avoid: health, RAG, risk
Week: A column of the plan: one real calendar week, identified and labelled by the date of its first workday (Monday). Columns run contiguously from the earliest Feature start to the last marker or Milestone — empty weeks in between are still drawn. An optional authored start/end widens this span with lead-in or trailing empty Weeks; it only ever extends the range, never narrowing it or hiding a Feature. Avoid: column, period, sprint
Now line: A vertical line marking the current week across the whole plan — the at-a-glance "where are we right now". Avoid: today marker, cursor
Library:
The collection of saved Macroplans held in the browser's localStorage — the live store. Always holds at least one Macroplan; durability rests on exporting a Macroplan's .toml (per ADR-0002), not on the Library itself. Carries no status of its own.
Avoid: workspace, project, file list
Format version:
Which revision of the portable Macroplan .toml format a file targets, declared by an optional top-level macroplan_version (currently 1). Absent means the current version; a newer version is rejected rather than silently mis-rendered. The format — its fields and render semantics — is defined in docs/format.md so a Macroplan can be produced or consumed outside this app.
Avoid: schema version, file version, app version
Symbols
┣start of a Feature's bar━continuation of the bar◯Original Estimate, not yet delivered◉delivered on time (on/before Original Estimate)△Re-estimate (a slip to a later week)▲delivered late (after Original Estimate)
Relationships
- A Macroplan contains a flat, author-ordered list of Features (typically ordered by start Week) and many Milestones. There is no grouping/workstream concept.
- The Library holds many Macroplans, exactly one of which is active (shown in the editor and grid). Each is identified internally by a stable id and labelled by its title.
- A Feature has exactly one Original Estimate, zero or more Re-estimates, at most one Delivery, and at most one Learning.
- A Milestone explicitly names the Features required by it; a Feature may be required by zero, one, or several Milestones, and a Feature may be in the plan without belonging to any Milestone.
- On-time vs. late is judged against the Original Estimate, never a Re-estimate.
Example dialogue
PM: "Feature C had a
◯in W3 but we slipped — put a△in W5." Dev: "And when it actually shipped in W6, it's▲late, because we judge against the original W3◯, not the W5 re-estimate." PM: "Right. The slip and the late delivery are both visible — that's the Learning."