# Macroplan
|
||||
|
||||
A **Macroplan** is a week-granular view of the features we've committed to deliver — a simpler cousin of a Gantt chart whose purpose is not just scheduling but *learning* from how our estimates held up over time.
|
||||
|
||||
## Language
|
||||
|
||||
**Macroplan**:
|
||||
A week-granular plan of the **Features** we've committed to deliver, read as a record of how estimates held against reality.
|
||||
_Avoid_: Gantt, roadmap, timeline
|
||||
|
||||
**Feature**:
|
||||
A unit of delivery with a start week, an **Original Estimate**, optional **Re-estimates**, and (eventually) a **Delivery**.
|
||||
_Avoid_: task, ticket, story, epic
|
||||
|
||||
**Original Estimate**:
|
||||
The first committed delivery week for a Feature. The immovable baseline against which on-time vs. late is judged. Rendered `◯` while unmet.
|
||||
_Avoid_: target, deadline, due date
|
||||
|
||||
**Re-estimate**:
|
||||
A revised, later delivery week recorded when a Feature will miss a prior estimate. A visible slip; it never moves the Original Estimate baseline. Rendered `△`.
|
||||
_Avoid_: reschedule, new deadline
|
||||
|
||||
**Delivery**:
|
||||
The week a Feature was actually completed. On-time (delivered on/before the Original Estimate) renders `◉`; late renders `▲`.
|
||||
_Avoid_: completion, done date, release
|
||||
|
||||
**Milestone**:
|
||||
An external event or date that explicitly names a set of Features that must be delivered by it. Rendered as a labelled vertical line across the plan. Carries no rolled-up status of its own — whether it will be hit is read off its Features.
|
||||
_Avoid_: deadline, release, gate
|
||||
|
||||
**Learning**:
|
||||
A free-text takeaway captured against a Feature once it is delivered — what this delivery taught us to do better next time. Shown in a persistent trailing column per row; empty for in-flight Features.
|
||||
_Avoid_: retro note, lesson, postmortem
|
||||
|
||||
**Status**:
|
||||
A Feature's *current* delivery confidence (a snapshot, overwritten each review): **green** (all good), **orange** (in trouble but we have a plan), **red** (in trouble and we have no plan). May carry a comment. Applies only while in-flight; once delivered, the **Learning** takes over and the Status is dropped. An overdue Feature (past its latest estimate, not delivered) is expressed through an orange/red Status, not a dedicated symbol.
|
||||
_Avoid_: health, RAG, risk
|
||||
|
||||
**Week**:
|
||||
A column of the plan: one real calendar week, identified and labelled by the date of its first workday (Monday). Columns run contiguously from the earliest Feature start to the last marker or Milestone — empty weeks in between are still drawn.
|
||||
_Avoid_: column, period, sprint
|
||||
|
||||
**Now line**:
|
||||
A vertical line marking the current week across the whole plan — the at-a-glance "where are we right now".
|
||||
_Avoid_: today marker, cursor
|
||||
|
||||
## Symbols
|
||||
|
||||
- `┣` start of a Feature's bar
|
||||
- `━` continuation of the bar
|
||||
- `◯` Original Estimate, not yet delivered
|
||||
- `◉` delivered on time (on/before Original Estimate)
|
||||
- `△` Re-estimate (a slip to a later week)
|
||||
- `▲` delivered late (after Original Estimate)
|
||||
|
||||
## Relationships
|
||||
|
||||
- A **Macroplan** contains a flat, author-ordered list of **Features** (typically ordered by start **Week**) and many **Milestones**. There is no grouping/workstream concept.
|
||||
- A **Feature** has exactly one **Original Estimate**, zero or more **Re-estimates**, at most one **Delivery**, and at most one **Learning**.
|
||||
- A **Milestone** explicitly names the **Features** required by it; a Feature may be required by zero, one, or several Milestones, and a Feature may be in the plan without belonging to any Milestone.
|
||||
- On-time vs. late is judged against the **Original Estimate**, never a **Re-estimate**.
|
||||
|
||||
## Example dialogue
|
||||
|
||||
> **PM:** "Feature C had a `◯` in W3 but we slipped — put a `△` in W5."
|
||||
> **Dev:** "And when it actually shipped in W6, it's `▲` late, because we judge against the original W3 `◯`, not the W5 re-estimate."
|
||||
> **PM:** "Right. The slip and the late delivery are both visible — that's the **Learning**."
|
||||